| |
|
|
Pinnacle
Design/Build has successfully designed and constructed hundreds of
thousands of earth and water retention structures in support of
commercial and retail development projects throughout the United
States. Our ability to work with developers and architects to design and
construct walls and other structures that are functional as well as
aesthetically fitting has allowed Pinnacle Design/Build to become one a
preferred specialty subcontractor to service this industry. In
addition, we often make design recommendations that substantially reduce
the cost of earth retention without sacrificing the developer’s vision
for a project.
Pinnacle Design/Build -
Commercial/Retail Project Profiles
|
 |
|
Home Depot,
Villa Rica, GA
PROJECT
FACTS:
Slope
Area
= 31,000 SF;
Max Ht
= 32 FT
CHALLENGE:
Create a grade separation along the property line to support
the new store and parking lot.
SOLUTION:
Pinnacle Design/Build provided a 32 ft tall Vegetated MSE
vegetated slope as a value added alternative.
VALUE:
The Vegetated MSE vegetated slope was constructed faster and
eliminated utility conflicts with utilities adjacent to the
slope. The “green” solution allowed the very tall steepened
slope to blend into the natural surroundings.
|
|
 |
|
Marketplace at Birmingham Village,
Alpharetta, GA
PROJECT
FACTS:
Wall Area
= 17,760 SF;
Max Ht
= 18 FT
CHALLENGE: The commercial developer required the site storm water
detention basins to be more cost effective than cast
in place concrete.
SOLUTION: Our engineers redesigned the detention basin walls from
all cast-in-place concrete to a composite vegetated
welded wire form
/cast in place retaining wall.
VALUE: This solution provided 35% cost savings over the
previously designed wall and provided more pleasing
appearance.
|
|
 |
|
Home Depot,
New Albany, IN
PROJECT
FACTS:
Wall Area
= 3,500 SF;
Max Ht
= 20 FT
CHALLENGE: This retail store was positioned into a hillside cut at
the rear of this site.
The cut required permanent support to allow
for the
construction of the rear access drive.
SOLUTION: A permanent Soldier Pile Retaining Wall with wood
lagging was constructed to support the hill side
excavation.
VALUE: The Soldier Pile Retaining Wall was constructed quickly
and allowed for store construction to progress
unimpeded.
|
|
 |
|
Lenoir Business Park,
Lenoir, NC
PROJECT
FACTS:
Wall
Area
= 94,000 SF;
Max Ht
= 56 FT
CHALLENGE:
The developer of this project required nearly 100 acres of
relatively flat space to construct several buildings and
associated parking. The project, located in the hilly
region of western North Carolina was on a fast track and the
reinforced slopes were on the critical path of the project
schedule.
SOLUTION:
Pinnacle Design/Build engineered and constructed four
massive MSE Vegetated slopes that averaged over 38 feet in
height.
VALUE:
Pinnacle Design/Build was able to make engineering decisions
during the design and construction process that allowed the
grading contractors to move at an expedited pace and stay on
schedule. In addition, the vegetated slopes blended nicely
with the surrounding area and were less expensive than other
options considered.
|
|
 |
|
Piedmont West,
Atlanta, GA
PROJECT
FACTS:
Wall
Area
= 5,300 SF;
Max Ht
= 18 FT
CHALLENGE:
The commercial development required retaining walls to
create a below grade stormwater detention pond on a
congested construction site with limited right of way.
SOLUTION:
Pinnacle Design/Build designed and constructed a tied-back
soldier pile and lagging walls with a cast-in-place concrete
facing on three sides of the structure and a segmental
retaining wall on the fourth.
VALUE:
The Pinnacle Design/Build solution enabled construction of
the stormwater detention basin within the limited confines
available. The solution provided a substantial cost savings
over the originally designed cast in place concrete
retaining walls.
|
|
 |
|
Home Depot,
Inverness, AL
PROJECT
FACTS:
Wall Area
= 8,000 SF;
Max Ht
= 37 FT
CHALLENGE:
The retail site’s extreme change in grade required a
retaining wall to support the store’s rear access drive.
SOLUTION:
A MSE Segmental Retaining Wall was the solution selected by
the Pinnacle Design/Build design team for the structural
support of the fill for the rear access drive.
VALUE:
The selected MSE Segmental Retaining Wall system’s high
structural performance provided the required support for the
37ft fill while offering an appealing architectural finish.
|
|
 |
|
Atlantic Station,
Atlanta, GA
PROJECT
FACTS:
Wall Area
= 23,000 SF;
Max Ht
= 15 FT
CHALLENGE:
The developer was required to support an earth fill adjacent
to a depressed parking deck. The retaining wall had to
allow vehicular traffic to cross over the top of the
retaining wall into the parking deck.
SOLUTION:
Pinnacle Design/Build engineered and constructed a segmental
retaining wall with a cap beam. The project’s parking deck
structural engineer designed a cantilever road section to
span into the upper deck.
VALUE:
The retaining wall was installed at lower cost than
conventional cast in place concrete.
|
|
 |
|
Lowe's Home Improvement,
Henderson, TX
PROJECT
FACTS:
Wall Area
= 15,800 SF;
Max Ht
= 27 FT
CHALLENGE:
The retail developer had to maximize the useable land on
this site to accommodate the new store.
SOLUTION:
Pinnacle Design/Build constructed both MSE vegetated
retaining walls and the MSE segmental block walls along the
property edge.
VALUE:
The retaining wall structures were installed at lower cost
than conventional types. The “green” retaining wall blended
well with the stream channel.
|
|
|
|
|
|
|
|