| |
|
|
As opposed
to large cast-in-place foundations to support soil and building loads
for below-grade construction, Pressure Relief retaining walls can
provide a faster, more affordable solution for addressing this critical
construction need. Because the system effectively reinforces surrounding
fill, lateral soil loads against the below-grade structure are
eliminated allowing for lower cost foundation walls that are
structurally equivalent to conventional methods. Low cost materials and
speedy construction make pressure relief applications the system of
choice to replace counterfort walls and reduce concrete reinforcement in
structural foundation walls. This system is also the ideal alternative
to complete demolition and replacement of an existing structure in order
to accommodate increased loads due to facility expansion.
Pinnacle Design/Build
Pressure Relief Retaining Wall Project Profiles
|
 |
|
Piedmont West,
Atlanta, GA
PROJECT
FACTS:
Wall
Area
= 9,000 SF;
Max Ht
= 30 FT
CHALLENGE:
A below grade parking structure required thick, expensive
reinforced concrete retaining walls to support lateral earth
pressures and the structure to be constructed above it.
SOLUTION:
Pinnacle Design/Build value engineered and constructed a
composite soil nail and MSE retaining wall system to
withstand the anticipated lateral loads. A segmental block
facing was constructed in front of the composite mass to
form the permanent interior wall facing for the parking
garage. This eliminated the need to build an additional
facing wall.
VALUE:
The developer was able to save about 40% of the cost of
traditional foundation walls and cut the timeline for
completion by about 30%.
|
|
 |
|
Foundry Park,
Richmond, VA
PROJECT
FACTS:
Slope
Area
= 17,100 SF;
Max Ht
= 43 FT
CHALLENGE:
A below grade parking structure was designed with 48-inch
thick reinforced concrete foundation walls to support
lateral earth pressures and the structure to be constructed
above it. The structural engineer was looking for ways to
reduce the cost of these walls for the developer.
SOLUTION:
Pinnacle Design/Build value engineered and constructed a
composite an MSE retaining wall system to withstand the
anticipated lateral loads.
VALUE:
This solution reduced the cost of the foundation walls on
the project by approximately 50 percent and allowed the
project to proceed ahead of schedule.
|
|
 |
|
Two Alliance Center,
Atlanta, GA
PROJECT
FACTS:
Wall
Area
= 12,000 SF;
Max Ht
= 48 FT
CHALLENGE:
A new office building was to be erected in the tight
confines of the Buckhead area of Atlanta. The foundation
walls of the adjacent below-grade parking structure were
supported by a temporary, tied-back piling wall that was not
designed to support the new structure. A permanent pressure
relief wall was required.
SOLUTION:
Pinnacle Design/Build designed and constructed an MSE
pressure relief wall that allowed the facing of the existing
pile wall to remain in place while supporting the
anticipated design loads of the new structure.
VALUE:
This solution significantly reduced the overall cost and
time required to prepare the site for construction by
eliminating the requirement to demolish the existing
temporary wall. The entire wall was constructed in less
than two months.
|
|
| |
|
|
|
You must have the Adobe
Acrobat Reader to view our brochures, newsletters, etc. You can get the
Adobe Acrobat Reader
for Free! |
|
|