Public Works Project Profiles
|
 |
|
Lake Fork Water Pump Station,
Alba, TX
PROJECT
FACTS:
Wall
Area
= 6,000 SF;
Max Ht
= 33 FT
CHALLENGE:
The new Lake Fork Pump Station under construction for the
City of Dallas required retaining walls at the water intake
structure. When in service, the bottom 2/3 of these walls
would be submerged and subject to water level fluctuation as
well as wave action.
SOLUTION:
Pinnacle Design/Build designed and constructed a large block
MSE retaining wall as a value engineering alternative to
massive cast-in-place concrete retaining walls.
VALUE:
The engineered solution yielded a 30% to 40% cost savings
over the original cast-in-place concrete design while
providing the structural stability required and improving
the aesthetic appeal.
|
|
 |
|
Beech Creek Water Improvements,
Franklin, TN
PROJECT
FACTS:
Wall Area
= 10,500 SF;
Max Ht
= 29 FT
CHALLENGE:
The Mallory Valley Utility District in Williamson County,
Tennessee required two new five million gallon water tanks
as part of a large public water supply improvement project.
To meet elevation requirements, the tanks were to be
situated near the top of a steep hillside. However, a
stable and level foundation was necessary to support the
heavily loaded tanks.
SOLUTION:
Pinnacle Design/Build designed and constructed two
mechanically stabilized earth segmental retaining walls to
safely carry the anticipated loading associated with the
tanks.
VALUE:
The Pinnacle Design/Build solution provided a quick and cost
effective solution to develop the foundation area required
for the new water tanks and allowed the project to
continue on schedule.
|
|
 |
|
Buffalo Bayou Bank Protection,
Houston, TX
PROJECT
FACTS:
Slope
Area
= 3,000 SF;
Max Ht
= 10.5 FT
CHALLENGE:
As part of a City of Houston Parks jogging and bike path
improvement project, retaining walls were required at new
bridge structure to be constructed over the Buffalo Bayou
drainage channel. These walls needed to provide structural
support for the bridge, protect the bank of the bayou from
erosion and fit with the natural surroundings of the park.
SOLUTION:
As part of a City of Houston Parks jogging and bike path
improvement project, retaining walls were required at new
bridge structure to be constructed over the Buffalo Bayou
drainage channel. These walls needed to provide structural
support for the bridge, protect the bank of the bayou from
erosion and fit with the natural surroundings of the park.
VALUE:
The Pinnacle Design/Build solution provided a surprisingly
cost effective and green solution that satisfied city
officials as well as park goers.
|
|
|
|
|
|
|
|