|
|||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||
| Pinnacle Retaining Wall and Erosion Control Systems |
Above- and Underground Stormwater Detention Structures |
||||||||||||||||||||||||||||||||||||||||||||||||||
|
Today, just about every land development project requires storm water management. Storm water discharges are generated by runoff from land and impervious areas such as paved streets, parking lots, and building rooftops during rainfall and snow events. Storm water management is a high priority for local communities, particularly in urban/suburban areas. The best way to mitigate storm water impacts from new developments is the use of practices to treat, store, and infiltrate runoff onsite before it can affect water bodies downstream.
For more than 12 years, Pinnacle Design/Build has designed and built
retaining walls and erosion control systems to manage storm water in a
variety of situations.
|
|||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
||
![]() |
Marketplace at Birmingham Village,
Alpharetta, GA PROJECT FACTS: Wall Area = 17,760 SF; Max Ht = 18 FT
CHALLENGE: The commercial developer required the site storm water
detention basins to be more cost effective than cast
in place concrete.
SOLUTION: Our engineers redesigned the detention basin walls from
all cast-in-place concrete to a composite vegetated
welded wire form
/cast in place retaining wall.
VALUE: This solution provided 35% cost savings over the
previously designed wall and provided more pleasing
appearance.
|
|
|
|
||
![]() |
Stonewyck Detention Basin,
Alpharetta, GA PROJECT FACTS: Wall Area = 5,000 SF; Max Ht = 20 FT
CHALLENGE: The residential developer for this project required a storm water detention basin that was more cost effective and aesthetically pleasing than the continuous cast in place concrete wall originally designed for the project.
SOLUTION: Our engineers redesigned the detention basin wall from a single large cast-in-place concrete wall to a composite segmental retaining wall/cast in place concrete retaining wall. We constructed the concrete wall first then butted the segmental retaining wall into it.
VALUE: This solution provided 25% cost savings over the previously designed wall and provided more pleasing appearance.
|
|
|
|
||
![]() |
Piedmont West, Atlanta, GA PROJECT FACTS: Wall Area = 5,300 SF; Max Ht = 18 FT
CHALLENGE: The commercial development required retaining walls to create a below grade stormwater detention pond on a congested construction site with limited right of way.
SOLUTION: Pinnacle Design/Build designed and constructed a tied-back soldier pile and lagging walls with a cast-in-place concrete facing on three sides of the structure and a segmental retaining wall on the fourth.
VALUE: The Pinnacle Design/Build solution enabled construction of the stormwater detention basin within the limited confines available. The solution provided a substantial cost savings over the originally designed cast in place concrete retaining walls.
|
|
|
|
||
![]() |
Highridge Industrial Park,
Houston, TX PROJECT FACTS: Wall Area = 11,000 SF; Max Ht = 11 FT
CHALLENGE: The developer of this industrial park wanted to increase his usable space by reducing the footprint of the required onsite stormwater detention pond . The Civil Engineer had recommended replacing the originally designed 3H:1V pond side slopes with near vertical cast-in-place concrete retaining walls.
SOLUTION: Pinnacle Design/Build designed and constructed near vertical MSE vegetated slopes in lieu of cast-in-place concrete walls.
VALUE: Our solution allowed the developer to effectively reduce the footprint of his detention pond and significantly decrease construction costs versus traditional cast in place concrete walls.
|
|
|
|
||
![]() |
Providence Marketplace,
Mt. Juliet, TN PROJECT FACTS: Wall Area = 14,000 SF; Max Ht = 22 FT
CHALLENGE: The developer of this retail site was required to create a storm water detention structure in high ground water table and exposed surface rock conditions.
SOLUTION: Pinnacle Design/Build engineered and constructed a composite wall system consisting of a free standing cast-in-place concrete wall abutted to a stone faced MSE wall.
VALUE: This solution reduced the overall cost of the structure by reducing the amount of cast-in-place concrete required. In addition, the design was easily adapted to meet the difficult ground water and surficial rock conditions.
|
|
|
|
||
![]() |
GeoStorage®
Prototype,
Weirton, WV PROJECT FACTS: Storage Volume = 12,000 CF (Dimensions: 49 FT x 73 FT x 6 FT); Vehicle Loading = AASHTO H20
CHALLENGE: The developer of the GeoStorage underground detention system needed to construct a prototype of a new system being marketed to provide more cost effective solutions to conventional underground storm water detention systems. The system had never been constructed in full scale.
SOLUTION: Our engineers and construction managers provided the know-how to make the concept reality. The system was constructed without problems and performed as expected.
VALUE: By proving that the system could be built as designed, Pinnacle Design/Build helped to introduce a new system that will cut the overall cost of underground storm water detention by 25 to 50%!
|
|
|
|
||
| You must have the Adobe Acrobat Reader to view our brochures, newsletters, etc. You can get the Adobe Acrobat Reader for Free! | ||
Copyright © 2011 Pinnacle Design Build Group, Inc. | Site Map | Privacy Policy | Retaining Wall Systems